This project involves the construction of a new 110kV substation in an industrial park in Uzbekistan, aimed at meeting the rapidly growing power demand and improving the reliability of the regional power grid.
The substation adopts a 110/35kV voltage configuration with an outdoor AIS (Air Insulated Substation) design. The scope covers high-voltage switchgear, metering systems, protection and control systems, and a complete grounding network.
Project scope includes:
· Construction of 110kV substation system
· Installation of high-voltage equipment (SF6 circuit breakers, disconnect switches, etc.)
· Busbar system installation
· Protection and automation system integration
· System commissioning and energization
During the supplier selection phase, the client evaluated multiple vendors based on:
· Equipment reliability and service life
· Experience in 110kV substation projects
· Technical support and installation capability
· Delivery time control
· After-sales service responsiveness
Eberry Electric was selected due to:
· Proven experience in high-voltage substation projects
· Comprehensive MV & HV product portfolio
· Integrated support from supply to installation guidance
· Fast and professional engineering response
After project confirmation, both parties completed technical parameter verification and optimized the system design to ensure compatibility with site conditions.
Strict quality control was implemented during production, including:
· Mechanical performance testing
· Insulation level verification
· Withstand voltage testing
· Pre-delivery inspection
All equipment was thoroughly tested before shipment to ensure smooth on-site installation.
Upon delivery, technical support was provided to assist with:
· Equipment positioning and installation
· Busbar connection
· Secondary wiring
· System commissioning
Due to site constraints, equipment installation and lifting operations were complex.
Solution:
Optimized equipment layout and adopted modular installation methods to improve efficiency.
The client required a strict and fast delivery timeline.
Solution:
· Prioritized key equipment production
· Optimized logistics planning
· Coordinated installation and commissioning in parallel
The project milestones were completed on schedule.
Some protection signals showed instability during system testing.
Solution:
· Remote technical diagnostics
· On-site wiring inspection guidance
· Control logic and parameter optimization
· We dispatched two technical engineers to the project site for on-site commissioning. The issue was fully resolved, and the system returned to normal operation within one week.
During the initial operation phase, the client encountered minor issues related to system operation and monitoring.
We provided:
· Remote technical support
· Operation guidance and training
· Parameter adjustment assistance
This ensured a smooth transition to stable operation.
The client expressed high satisfaction with the project:
· Stable equipment performance
· Smooth installation process
· On-time delivery
· Responsive and professional technical support
The 110kV substation is now operating reliably, providing continuous and stable power supply to the industrial park.
It has significantly improved:
· Power supply capacity
· Grid stability
· Operational reliability for industrial users
This project demonstrates Eberry Electric’s capability in delivering complete high-voltage power solutions, from equipment supply to successful commissioning.
With reliable products, professional support, and efficient execution, we ensure the successful implementation of substation projects worldwide
Phone: +8613736779975
E-mail: sales@vcbbreaker.com
Address: 66 Punan Road, Yueqing Economic Development Zone, Zhejiang, China
New energy: www.prominentcn.com
Copyright © 2025 Eberry Electric Group All rights reserved
This website uses cookies to ensure you get the best experience on our website.
Comment
(0)